Drainage work progress




2 days to completion



Wednesday 25th March

Job finished other than tarmac areas in car park which will be done next week. Block paving in car park finished and stone put on other parking area. Areas of trench that were left rough cemented over to give smoother finish. Site cleared up.

Photos page 1 Photos page 2 Photos page 3

Tuesday 24th March

Block paving in car park almost finished. Steps finished and front fence put back.

Photos

Monday 23rd March

More concrete put in trench. Trench work now completed.

Photos page 1 Photos page 2

Friday 20th March

Chambers finished. Trench partially filled with concrete. Reconstruction of steps and block paving started.

Photos page 1 Photos page 2

Thursday 19th March

Connection under paving by clubhouse made. Drain tested. Stone infill put in.

Photos

Wednesday 18th March

Base of chambers put in and pipes connected between them all.

Photos page 1 Photos page 2

Tuesday 17th March

Trench now connects from clubhouse to car park. Areas for chambers dug out.

Photos

Monday 16th March

There is now just the bit of trench across the corner of court 3 to dig.

Photos

Friday 13th March

The trench is now half way across court 2. No snags today.

Photos page 1 Photos page 2

Thursday 12th March

The trench has now turned the corner and is nearly halfway along the fence. No snags today.

Photos page 1 Photos page 2

Wednesday 11th March

The trench reaches the back fence. No more pipes found but what is thought to be a water pipe has now been found to cross from one side of the trench to the other.

Photos page 1 Photos page 2

Tuesday 10th March

Trench work outside clubhouse started. Two pipes discovered running parallel to trench. Due to pipes trench has to be dug further away from clubhouse. Later a third pipe is discovered running parallel to the new trench.

Photos page 1 Photos page 2

Monday 9th March

Trench dug to within a couple of feet of the fence, pipe laid and trench backfilled. Skip delivered. Photos

Friday 6th March

Trench dug to connect to foul drain in car park. Unexpected amount of concrete backfill discovered that had to be broken through in order to break into chamber. Connection made to foul drain. Photos

Thursday 5th March

Pipes stored on court 1. Block paving in car park taken up. Tarmac near manhole cut with disc cutter. Gravel delivered. Photos

Wednesday 4th March

Car park area fenced off, sheets of hardboard stored on court 1. Photos

Tuesday 3rd March.

Nothing done.

Monday 2nd March

Start of project. Nothing done.