Refurbishment of courts 1 and 2
6 days past expected completion date (weather permitting)
Thursay 16th April
Nothing done.
Tuesday 7th April
Red texture coat appllied.
Monday 6th April
Green texture coat appllied.
Friday 3rd April
New rubber mat laid.
Thursday 2nd April
Worn areas of rubber cut out. Exposed tarmac jet washed. Note amount of sand that was under the rubber.
Monday 30th March work starts
Both courts power washed.